GPC BUILDINGS, FISCAL YEAR 1997 - 1998

 

Location

 

Number of

Buildings

 

Acreage

Gross

Square

Footage

Average

Replacement

Cost (@ $77.31/SF)

 

Content

Values

Clarkston 15 57.59 508,505 $39,312,522.00 $10,671,067.00
Decatur 11 58.04 194,091 15,005,175.00 6,561,964.00
Dunwoody 14 76.27 246,091 19,025,292.00 5,413,819.00
Lawrenceville 3 N/A 81,906 N/A 945,476.00
Rockdale 1 N/A 20,044 N/A 149,227.00
Total 44   1,050,637   $23,741,553.00


MAJOR IMPROVEMENTS AND RENOVATION PROJECTS

GPC, Fiscal Year 1997 - 1998

Fiscal Year 1997:  
Clarkston Campus  
Building C – Renovation $180,736.00
Building I – Renovation 516,732.00
Building J – Renovation 244,171.00
F Building – Renovation 25,602.00
Building A – Renovation 14,074.00
Building D, E & G – Roof Repair 98,849.00
Building S – Renovation 23,414.00
Dunwoody Campus  
Building B – Roof Replacement 191,895.00
Building A, C & D – Roof Repair 75,000.00
Decatur Campus  
Building C – Renovation 111,602.00
Building C – Roof Replacement 145,000.00
Building B – Roof Repair 75,000.00
Building A & B – Upgrade HVAC 63,467.00
Building A– LRC – Renovation 222,572.00
   
Fiscal Year 1998:  
Clarkston Campus  
Repair Covered Walkways - Campus-Wide 398,500.00
ADA Restroom Renovation - Bldg. CH 79,500.00
Fire Alarm Replacement - Campus-Wide 130,700.00
Continuing Education Heating & AC 93,881.00
Asbestos Floor Tile Abatement - Bldg. CD 21,876.00
   
Decatur Campus  
Replace Boiler - Bldg. SC 120,712.00
Masonry Restoration - Bldg. SA 53,835.00
New Computer Classrooms - Bldg. SD 135,118.00
   
Lawrenceville Campus  
New Science Lab - Bldg. RB 85,804.00

    Source: Office of Finance